1.Steel upper floating body manufactured in a plant is connected with concrete-made lower floating body at the quay to complete the hybrid spar-type floating body.
2.The floating body(hybrid spar type) is loaded onto a salvage barge and transported to the assembly site in the sea north of Kabashima.
3.The floating body is lifted and raised by a large floating crane,and floated on the sea.
4.The tower, nacelle and rotor are attached to the floating body,which completes the wind turbine.
5.After its completion, the wind turbine is towed from the assembly site in the sea north of Kabashima to the installation site.
6.To complete the installation, mooring chains and submarine cables are connected to the turbine at the installation site.