Up to completion of wind turbine Haenkaze

process_01
1.Steel upper floating body manufactured in a plant is connected with concrete-made lower floating body at the quay to complete the hybrid spar-type floating body.
process_02
2.The floating body(hybrid spar type) is loaded onto a salvage barge and transported to the assembly site in the sea north of Kabashima.
process_03
3.The floating body is lifted and raised by a large floating crane,and floated on the sea.
4.The tower, nacelle and rotor are attached to the floating body,which completes the wind turbine.
process_04
process_05
5.After its completion, the wind turbine is towed from the assembly site in the sea north of Kabashima to the installation site.
process_06
6.To complete the installation, mooring chains and submarine cables are connected to the turbine at the installation site.