Sakiyama 2MW Floating Offshore Wind Turbine
Installation site
						Summary of Sakiyama 2MW Floating Offshore Wind Turbine (Haenkaze)
						| Name: | Haenkaze(Non-self-propelled vessel) | 
|---|---|
| Location: | Approx. 5km off Sakiyama Fishing Port, Shimosakiyama-cho, Goto City, Nagasaki Prefecture | 
| Shape and dimensions: | Total length 172m (Draft: 76m, Hub height: 56m, Rotor diameter: 80m) Floating body diameter: Maximum 7.8m Tower diameter: Maximum 4.8m  | 
									
| Weight: | About 3,400 tons(without mooring) | 
| Structure type: | Hybrid spar | 
| Mooring system: | Three-point catenary mooring system (Steel chains) | 
| Wind turbine generator: | Downwind (Maximum power output: 2,000kW) | 
| Others: | Submarine cable: Total length about 5km | 
Transmission of electric power
The Haenkaze is the first floating wind turbine in Japan. The power generated is sent through subsea cable and distributed to households via a substation.
						Floating meteorological tower
						| Name: | Toki(Non-self-propelled vessel) | 
|---|---|
| Location: | Approx. 2.0km southwest of Takanosuhana-todai lighthouse, Kabashima,Goto City, Nagasaki Prefecture | 
| Shape and dimensions: | Total length 71.2m (Draft: 37.05m, Hub height: 28.2m) Floating body diameter: Maximum 3.8m Tower diameter: Maximum 2.375m  | 
									
| Weight: | About 400 tons(without mooring) | 
| Structure type: | Hybrid spar | 
| Mooring system: | Three points catenary mooring system (Steel chains) | 
| Meteorological device: | 3D ultrasonic Anemometer | 
| Others: | Navigation light: White Morse code (16 candela, 4 lights, visible distance: 3.0 nautical miles) Power supply from solar light and fuel cell The half-scale experiment model which was installed in FY2012 was remodeled into the floating meteorological tower. It has now been moved.  |